Chester County roadwork to watch out for this week
Drivers, take note of these possible delays and detours that could cause traffic across several municipalities.

Roadwork will cause detours, delays, and closures in nine municipalities throughout the county this week.
A little good news, though: PennDot has reopened a section of Bondsville Road in Caln and East Brandywine Townships, which was closed for a $1.9 million retaining wall project. Work on the wall is expected to continue through next November.
Here are the traffic changes you need to know as of Nov. 24:
Caln Township: Caln Road will be closed between Blackhorse Hill Road and Jennifer Drive from 9 a.m. to 3 p.m. on weekdays through Nov. 30.
East Nantmeal Township: Iron Bridge is still closed for structural repairs. There’s no timeline yet for reopening.
Honey Brook and West Nantmeal Townships: Chestnut Tree Road will have a weekday lane closure between Horseshoe Pike and Manor Road from 8 a.m. to 4 p.m. through Nov. 24 for milling and paving.
North Coventry Township: Sanatoga Road will be closed between High Street and Linfield Road from Nov. 30 to Dec. 21 as part of PennDot’s $83.6 million project to improve roadways and replace bridges between the Sanatoga Interchange and Porter Road on Route 422. There will be periodic lane closures weekdays from 6 a.m. to 4 p.m. on Porter Road between High Street and Sanatoga Station Road from Nov. 30 to Dec. 14. There will also be a left lane closure and periodic stops on westbound Route 422 between the Sanatoga and Hanover Street interchanges from Dec. 1 to 3 from 7 p.m. to 7 a.m.
Phoenixville Borough: Jones Street will be closed from 7 a.m. to 5 p.m. between Second and Third Avenues for water line replacement work through about the end of November.
West Brandywine Township: Pratts Dam Road will be closed on Nov. 24 for tree work. East Reeceville Road will be closed for utility work between Sweet Briar Road and Sills Lane/Gala Road through Nov. 25.
West Whiteland Township: There will be potential delays on Whitroad Road from 7 a.m. to 3:30 p.m. through the end of the year for work on the Chester Valley Trail extension.
Willistown Township: A roughly three-week resurfacing project is slated to get underway Nov. 30 on Goshen Road, impacting sections between Sugartown and Delchester Roads and between Old Covered Bridge and Grubbs Mill Roads. Work will take place weekdays from 9 a.m. to 4 p.m. through Dec. 18.
This suburban content is produced with support from the Leslie Miller and Richard Worley Foundation and The Lenfest Institute for Journalism. Editorial content is created independently of the project donors. Gifts to support The Inquirer’s high-impact journalism can be made at inquirer.com/donate. A list of Lenfest Institute donors can be found at lenfestinstitute.org/supporters.